Hi, is there a way to visualize the different task dependency types in the Gantt Chart? There are four types:

  • Start-Start
  • Start-Finish
  • Finish-Finish
  • Finish-Start

Ideally, the direction from which the arrow connects to a task should represent the specific type of dependency between two tasks.

If not, would it be possible to add this feature to the Gantt Chart in the future?

Thanks for your help!

Hi!

Thanks for reaching out…

We only have functionality for start-to-finish task dependency right now and not the other three. However, we’ve done some research and it looks like we can add functionality for customising the dependency connectors. I’ll pass this wish on to the platform team.

Thank you for letting us know!

Thank you for considering my request! I appreciate it. I look forward to seeing the new functionality in the future :slight_smile: